State approves a $2.48 billion gas plant at Fort Martin and three solar projects

The Morgantown Daily News teamFrom Wednesday’s edition · 1 min read · 4 sources

ShareEmailFacebookX

If you're a Mon Power or Potomac Edison customer, this one touches your bill. The on Tuesday approved a 1,200-megawatt natural gas plant at the existing in Monongalia County, priced at $2.48 billion. It also approved 70 MW of solar, estimated at $182 million.

The gas plant's price tag is far bigger than the solar projects' cost

Sources: WAJR, WDTV 5

View as table
Value
Fort Martin gas plant$2,480 million
Three solar projects$182 million

The solar sites are Valley Point near Albright, Davis, and Wylie Ridge in Weirton. A surcharge will cover financing costs until they're included in base rates, and the companies estimate it will initially add about $1.18 a month, or 0.9%, to residential bills.

The companies cite a projected shortage from 2029 through 2045, and WBOY reports the initial pitch estimated a late 2031 opening. WV MetroNews reports several United Mine Workers members worry the plant would ultimately replace the coal-fired one.

  • Updates due: annual filings, starting January 2027
  • Notice: at least 30 days before construction begins
  • Case: 26-0108-E-CN, at psc.state.wv.us

The plant went from filing to approval in nine months

  1. FebruaryMon Power and Potomac Edison file their application.
  2. JulyThe PSC hears from residents and coal miners in Charleston.
  3. Nov. 17The PSC approves the gas plant and three solar projects.
  4. 2029The companies project a power shortage will begin.
  5. Late 2031The initial pitch estimated the plant would open.

Sources: WAJR, WDTV 5, WV MetroNews, WBOY.com