EnergyTop story
State regulators approve a $2.48 billion gas plant at Fort Martin in Maidsville
The Maidsville plan comes with big numbers
- $2.48 billion
- estimated cost of the gas plant
- 1,200 MW
- of natural gas generating capacity
- 70 MW
- of added solar capacity
- $1.18
- estimated monthly residential increase at first
Sources: WV MetroNews, The Dominion Post
The Public Service Commission approved Tuesday Mon Power and Potomac Edison's plan for the Maidsville Energy Center, a 1,200-megawatt gas plant at the Fort Martin site. It's the first major power plant in Monongalia County since 2011. FirstEnergy's Chris Beam told WAJR that construction starts next year and the plant should be operational by 2031.
If you're a Mon Power or Potomac Edison customer, here's the cost. The PSC approved a Generation Projects Surcharge that the companies estimate will raise residential bills $1.18 a month, or 0.9%, at first.
- Jobs: about 30 permanent; more than 2,000 construction workers at peak
- Solar: three sites, $182 million
- Next up: construction update in the PSC filings due January 2027
- Notice: companies must tell the PSC 30 days before construction
Not everyone's on board. Emmett Pepper of Energy Efficient West Virginia said ratepayer protections aren't adequate, and UMWA President Brian Sanson criticized the approval. Beam said the plant belongs to FirstEnergy and its power will be sold to its customers.
The Maidsville plant should be running by 2031
- Feb.Mon Power and Potomac Edison file their application with the PSC.
- Apr. 24Mon Power applies to PJM Interconnection for an interconnection agreement.
- Nov. 17The PSC approves the gas plant, solar sites and surcharge.
- Jan. 2027Companies' annual filings must update the PSC on construction and costs.
- 2031The Maidsville Energy Center should be operational.
Sources: WV MetroNews, The Dominion Post